“All disputes arising out of or in
connection with the present contract shall be finally settled under the Rules of
Arbitration of the International Chamber of Commerce by one or more arbitrators
appointed in accordance with the said Rules.”
Optional
ADR
"The parties may at any time, without prejudice to any other proceedings,
seek to settle any dispute arising out of or in connection with the present
contract in accordance with the ICC ADR Rules."
Obligation to consider ADR
"In the event of any dispute arising out of or in connection with the
present contract, the parties agree in the first instance to discuss and
consider submitting the matter to settlement proceedings under the ICC ADR
Rules."
Obligation to submit dispute to ADR with
an automatic expiration mechanism
"In the event of any dispute arising out of or in connection with the
present contract, the parties agree to submit the matter to settlement
proceedings under the ICC ADR Rules. If the dispute has not been settled
pursuant to the said Rules within 45 days following the filing of a Request for
ADR or within such other period as the parties may agree in writing, the
parties shall have no further obligations under this paragraph."
Obligation to submit dispute to ADR,
followed by ICC arbitration as required
"In the event of any dispute arising out of or in connection with the
present contract, the parties agree to submit the matter to settlement
proceedings under the ICC ADR Rules. If the dispute has not been settled
pursuant to the said Rules within 45 days following the filing of a Request for
ADR or within such other period as the parties may agree in writing, such
dispute shall be finally settled under the Rules of Arbitration of the
International Chamber of Commerce by one or more arbitrators appointed in
accordance with the said Rules of Arbitration."